Welcome to the McKay Road Overlay Project Updates Page
The City of Shelbyville is dedicated to keeping citizens informed about the upcoming McKay Road Overlay and Storm Water Project, set to begin in June 2024. We understand that construction projects can cause disruptions, and it is our priority to minimize any inconvenience for you.
McKay Road Overview Map (PDF)
McKay Road Project Plans (PDF)
Project Overview:
New Storm Sewer Installation: We will install 2100 feet of storm sewer on the south side of McKay Road, from Berwick Drive to Theobald Street. This work involves removing curbs and driveway approaches and digging trenches approximately 3-4 feet deep. Your access to home and driveway will only be restricted during pipe installation under your driveway. Contractors have assured us they can install about 150 feet of pipe per day, so any access restrictions should be brief.
Mill and Overlay: The top layer of concrete will be milled off, and a new layer of asphalt will be applied. The road will remain open during this process, though access may be limited occasionally.
Throughout the construction period, you will still have access to your homes. We encourage you to check the preliminary schedule and project updates here on this page.
Attached are maps for a clearer visual understanding of the project area, spanning from Berwick Drive to approximately 500 feet east of Theobald Street.
We appreciate your patience and cooperation as we enhance the infrastructure in our community. If you have any questions or concerns, please contact the City Engineering Office at 317-392-5102.
Updates:
Saw Cutting for the storm pipe will begin today. Traffic will be shifted off the south end of the road but two lanes of traffic will remain open. There will be limited closures as they saw cut across the road and at the intersections of Berwick Drive, Premier Street and Theobald Street. There will also be flaggers at the intersection of Berwick Drive while they do some potholing.
Starting Monday, July 22nd progress will continue east on McKay toward Theobald St.
ANNOUNCEMENT: McKay Road will begin one-way directional traffic westbound between Miller Street and Miller Avenue throughout August 2024 beginning August 5, 2024.
Please review the following traffic patterns to navigate this area of our community:
Local adjacent businesses, churches, and property managers were called and forwarded packets and maps regarding the project
Finalized route with Shelby Central Schools teams
Social media notifications and press releases were sent out.
If you need to bring in groceries, large items, or other necessities during this period, you are welcome to temporarily park in the construction lane for closer drop-off and convenience.
We appreciate your patience and cooperation as we work to enhance our community infrastructure.
All residential driveways have been complete.
Please proceed with caution and slow speed in the construction area. There are drop offs until the shoulder has been complete.
Tuesday September 3rd Mill & HMA Wedge west bound lane
Wednesday September 4th Mill & HMA Wedge east bound lane
Thursday September 5th Install Fabric, HMA Overlay & Temporary Tape Striping east bound and west bound lanes
Clearwick Resident Traffic Routes
Community Detour Traffic Routes
City of Shelbyville Engineering Department
The City of Shelbyville Engineering Department is dedicated to ensuring the safety, functionality, and sustainability of the city’s infrastructure. With a commitment to innovation and excellence, our team oversees various projects ranging from road maintenance and traffic management to stormwater management and public works initiatives. By collaborating with other departments and engaging with the community, we strive to enhance the quality of life for residents and visitors alike. Through meticulous planning, efficient execution, and a focus on continuous improvement, the Engineering Department plays a vital role in shaping the future of Shelbyville as a vibrant and thriving community.